Visit the HTMS web site

Transformer repair keeps power station online

An ABB Power Technologies product story
Edited by the Engineeringtalk editorial team Sep 5, 2007

ABB enabled Edenderry Power to avoid the major disruption and costly loss in production that would have resulted from sending the unit away for factory repair.

ABB's on-site transformer repair service has helped Edenderry Power Station in Ireland to achieve a fast-track return to normal production, and preserve the reliability of its output to the country's grid, by restoring its failing GSU (generator step-up unit) transformer to full working order.

The project, which was the first on-site repair carried out by ABB's UK power service team, was completed in just three weeks from start to finish, enabling Edenderry Power to avoid the major disruption and costly loss in production that would have resulted from sending the unit away for factory repair.

Furthermore, the total cost of the exercise came to around one tenth of the cost of a brand new transformer that, based on current lead times, would probably take two years from order to delivery.

Edenderry Power was Ireland's first large scale independent power producer and was recently acquired by Bord Na Mona.

It operates a 120MW peat-fired condensing power plant at Edenderry, 40 miles west of Dublin, that supplies around 3% of Ireland's national requirement.

The power station connects to the grid via a single GSU that steps its terminal voltage up to the 110kV required for transmission.

In March 2007, Edenderry Power noticed a problem with gassing of the transformer, indicating that a fault had developed, and decided to operate a reduced output, with a consequent reduction in energy efficiency.

ABB's UK power service team was called in and, after analysing daily gas samples and carrying out additional electrical tests, diagnosed an internal fault on the low-voltage connections and was able to locate its position.

Using the information from the diagnostic survey, ABB was able to re-assure Edenderry Power and its insurers that, for the short-term, it was safe for the transformer to remain in service.

However, it did need to be repaired before it could be turned to full load again, but with each day of reduced generation likely to cost the customer a significant amount of revenue, sending it away for factory repair was out of the question.

Liam Warren of ABB's UK power service operation said: "Internationally, ABB has a great deal of experience in carrying out on site transformer repairs".

"Until recently, the service was targeted at customers in remote parts of the world, such as Brazil, where the location and transport infrastructure make taking the transformer back to the factory both difficult and exceptionally expensive".

"But now we have seen a substantial shift in the drivers for this service".

"So now it is not really a question of geography as one of pure economics, dictated by the cost to the customer of having a transformer unavailable for service".

"In the case of Edenderry Power, the budget for the on-site repair was around GBP 250,000, which makes it extremely cost-effective compared to a new replacement transformer that might cost GBP 3 million".

"But as ABB and most of our competitors are quoting factory lead-times of around two years, buying new was not an option anyway".

"If we had taken the transformer back to the nearest repair factory, in Norway, there would have been some additional transport costs".

"The main concern though was the cost of lost production, as allowing for travel time and the factory work, the power station would be off line for at least six weeks, and possibly longer".

"By taking the factory to the site, ABB was able to reduce the power station's down time to just three weeks".

In July 2007, ABB's on-site repair team, comprising two transformer engineers and a transformer fitter, swung into action.

Their first task was to decommission the transformer.

Then a local heavy lifting specialist was called in to help move the transformer to a spare building at the power station that was converted into a temporary, fully-equipped, workshop, complete with clean room.

Working round the clock, the ABB team de-tanked the transformer, repaired it, re-assembled it and tested it on the spot.

A key element in the repair process was ABB's capability to carry out high-voltage tests and to commission the transformer ready to return to service.

The work was carried out to exactly the same standards that would be expected of a factory repair, with every phase conducted strictly to ISO9001 and ISO14001 procedures.

Tom Egan, Plant Manager for Edenderry Power, said: "The potential failure of the GSU transformer and consequent loss of production would have had serious financial implications for our business".

"The process went very smoothly and we are pleased to say that full energy efficient production has been restored".

Not what you're looking for? Search the site.

Back to top Back to top

Google Ads

 

Contact ABB Power Technologies

Related Stories

Contact ABB Power Technologies
Newsletter sign up

Request your free weekly copy of the Engineeringtalk email newsletter ...

Visit the HTMS web site

Articles by product category

All suppliers A - Z

A Pro-talk Publication

A Pro-talk publication