Visit the Eriks UK web site

Corrosion detector spots damage 3km down

An Arc Energy Resources product story
Edited by the Engineeringtalk editorial team Apr 7, 2008

The Ring Pair Corrosion Monitor (RPCM) is a high-resolution pipeline corrosion monitor developed for deepwater, high-pressure, high-temperature applications.

To keep the world's supply of oil and gas flowing, many of today's sub-sea carbon steel pipelines are dosed with chemical inhibitors to control corrosion caused by ever more aggressive fluid conditions.

As inhibitors are expensive, engineers need to measure the rate at which pipelines are corroding, in order to introduce chemicals at the right time and in optimum quantities.

A new solution to measuring corrosion rates 3km below the sea is manufactured by Cormon a provider of corrosion monitoring packages for the oil and gas industry.

The company's Ring Pair Corrosion Monitor (RPCM) is a high-resolution pipeline corrosion monitor developed for deepwater, high-pressure, high-temperature applications.

The piggable device, which is designed for lay barge installation, is butt welded into the pipeline, making it ideal for use in subsea oil and gas developments that have long pipelines tying them back to existing platforms or shore facilities.

Weld overlay cladding specialist Arc Energy Resources is Cormon's preferred supplier of welding and fabrication services, particularly for the RPCM spool, so when a recent order for ten units was placed for a major offshore gas infrastructure project in India, the two companies began a collaboration that produced one unit every week in a schedule that was only interrupted by a two-week break at Christmas 2007.

The order, the largest ever for RPCMs, was placed by Reliance Industries Limited (RIL), one of the first private sector companies in India's exploration and production sector to have discovered large gas reserves.

This new field is expected to provide natural gas for a vast numbers of India's burgeoning industries.

Because the pipeline is linked directly to a shore facility it is subjected to multiphase flows containing media such as water, oil and carbon dioxide, which is why RIL specified the latest high-resolution, dual-redundant RPCMs featuring remotely operated vehicle (ROV) retrievable electronics.

They provide real-time measurement to less than a micron, a level of accuracy that allows the pipeline operator to respond more quickly to corrosion problems in order to reduce chemical usage and extend the life of the pipeline.

As RPCMs are designed to be part of the pipeline, they must have the same performance characteristics as the pipeline itself, which is why Arc Energy's input is an essential element of Cormon's production planning.

Bob Davies of Cormon said "The electronics package in each RPCM includes a fixed instrument pod, ROV retrievable pod and an inner spool assembly".

"The sets were prefabricated by Cormon and delivered to Arc Energy with the main forgings and pipe sections".

"Arc Energy applied weld overlay cladding to the inside of the forgings, carried out the machine finishing and welded on sections of pipe, known as pup joints, to the forgings".

"Our engineers then installed the electronics and assembled the RPCM, at which stage Arc Energy performed the high-specification girth welds to join the halves together and then added end domes to prepare the unit for pressure testing".

"This stage, together with NDT testing and factory acceptance testing with our customer, was carried out at Arc Energy's Gloucestershire factory".

"The final stage was removal of the domes and preparation of the pipe for welding on the lay barge".

High-strength X65 steel was used, which means that welding procedures are critical and have to be meticulously qualified.

Bob Davies said "This is the first time we have needed to produce one unit a week and for an eight week period up to Christmas 2007 we actually completed one a week".

"It required a considerable amount of planning and teamwork between our two companies, which resulted in our engineers being onsite at Arc Energy for around 14 weeks in all".

"Meticulous planning was vital due to the volume of work and the timescales, as was the ability to repeat the production process week after week".

"But that's exactly what we achieved and if Christmas hadn't been in the way, we would have produced all ten in ten weeks.

"As it was, the delivery schedule was maintained throughout the project".

Not what you're looking for? Search the site.

Back to top Back to top

Google Ads

 

Contact Arc Energy Resources

Related Stories

Contact Arc Energy Resources
Newsletter sign up

Request your free weekly copy of the Engineeringtalk email newsletter ...

Visit the Eriks UK web site

Articles by product category

All suppliers A - Z

A Pro-talk Publication

A Pro-talk publication