Edited by the Engineeringtalk Editorial Team on 11 December 2006

Offshore wind farm requires submarine
power cable

Request your FREE weekly copy of the Engineeringtalk email newsletter. News about Cabling, Conduit, Accessories and Signal Conditioning and more every issue. Click here for details.

Nexans has signed a contract with Danish utility Energinet.dk to deliver and install the power export cable for Dong Energy's Horns Rev 2 offshore wind farm on the west coast of Denmark

This turnkey contract, worth around 30 million Euros, includes the supply of 42km of AC XLPE 170kV 3-core power cable including a fibre optic element, transport, laying and termination When the cable is installed, in Autumn 2008, it will become the world's longest XLPE submarine cable at this voltage

The Horns Rev 2 project will provide a total wind farm capacity of over 215MW and cover an area of some 35km2.

The project is situated around 23 km north west of Horns Rev 1, which in 2002 was the world's largest offshore wind farm, with a capacity of 160 MW, for which Nexans also delivered and installed the power export cables.

This time, however, the cable will be twice the previous length.

"We are particularly proud and happy that the Danish utility Energinet.dk has selected Nexans to be the turnkey contractor for the Horns Rev 2 project".

"This project is of strategic importance to Nexans as it represents an additional main turnkey reference that reinforces our strong position in the offshore wind farm market".

"Following the success of the Horns Rev 1 project in 2002, this new contract proves that a new major utility has complete confidence in Nexans' capabilities", said Executive Vice President Europe Area, Yvon Raak.

"The discussions between Nexans and Energinet.dk were very open and constructive".

"This helped us conclude the agreement within a relatively short period of time, and we will definitely maintain this open relationship during the project execution", said Sales Manager Olivier Angoulevant in Nexans Norway's Energy Division.

The 170 kV XLPE cable for Horns Rev 2 will be manufactured by Nexans' specialist submarine power cable factory in Halden, Norway.

The wind farm will be commissioned in May 2009.