Visit the James Walker and Co web site
Click on the advert above to visit the company web site

Product category: Process Hardware (Pipes, Nozzles, Heaters, etc)
News Release from: Rotork Controls | Subject: IQ2 intelligent electric actuators
Edited by the Engineeringtalk Editorial Team on 01 April 2004

Actuator upgrade adds intelligence to
gas terminal

Request your FREE weekly copy of the Engineeringtalk email newsletter. News about Process Hardware (Pipes, Nozzles, Heaters, etc) and more every issue. Click here for details.

Rotork is installing new electric actuators on around 300 major valves during a strategic modernisation and upgrade programme at the National Grid Transco gas terminal at Bacton in Norfolk.

Rotork has been awarded phased contracts to install new electric actuators on an approximate total of 300 major valves during a strategic modernisation and upgrade programme at the National Grid Transco (NGT) gas terminal at Bacton in Norfolk Rotork is replacing earlier versions of its own actuators which, in many cases, have been in operation since the Bacton plant first began processing North Sea natural gas in the early 1970s

Actuator replacement is being carried out by Rotork's specialist Site Services Department, working closely within the daily operational constraints of the site to minimise the risk of any interruption to normal plant operation.

The latest ATEX certified Rotork IQ2 intelligent electric actuators are being installed, the majority being IQ70 models operating buried service 36in Cameron pipeline ball valves.

Most of the valves control the movement of gas received from three North Sea gas producers situated on an adjacent site.

The gas undergoes filtering, blending and quality assurance processes, including checks on calorific value, volume, pressure and temperature, before it is pumped into the NGT National Transmission System.

For the last two phases Rotork took on the total installation responsibility, including the electrical work, and appointed Dabbrooks from Great Yarmouth to connect the actuators to Bacton's upgraded centralised monitoring and control system.

Each actuator provides continuous valve position and availability data, supported by alarm signals covering, for example, loss of power or incomplete valve movement.

As a part of the NGT-wide Ulysses Project, data from the Bacton control system are also being communicated by telemetry to NGT operational headquarters at Hinckley in Leicestershire.

Rotork's contracts are being performed in several stages.

Work began in 2002 and is expected to continue for another two years.

Rotork Controls: contact details and other news
Email this article to a colleague
Register for the free Engineeringtalk email newsletter
Engineeringtalk Home Page

Search the Pro-Talk network of sites

Visit the Dichtomatik web site
Visit the James Walker and Co web site