Crittall's 150 production staff completed their move in four months and maintained steel window production at 350 window frames per day thanks to the Teseo modular airline pipework system.

When Crittall Windows decided to move from its Braintree production site to a new 6039m2 factory 16km away in Witham, it used the Teseo modular aluminium airline pipework system.

The company had to make certain that the main power services were in place so that as machinery was installed in the new location it could be put into production right away.

Compressed air tools are used throughout the Crittall Window production lines and it was essential that this capacity was available from day one of the move.

Twin rotary screw compressors are the heart of the system delivering 68m3/min at an 8bar pressure to the driers and the 80mm internal diameter Teseo aluminium pressure ring.

"Our choice of the Teseo modular system was really determined by our very tight time frame for the move".

"The Teseo system is really so easy and so quick to install that while the product price may be higher than old fashioned galvanised steel, it is miles quicker to install, doesn't leak and does not rust".

"One man, even a semi-skilled fitter, can install a 50m run in an hour".

"The 5m sections are so easy to handle whereas, that length of steel is quite a weighty piece and the twin O-ring joints slide in easily and just clamp together".

"We had hangers for power line trays in place so the Teseo pipework was quickly hooked up".

"It is also so easy to add connections anywhere that you need it without shutting down the whole plant", said Mr Patchett.

Crittall installed its own Teseo airline system, featuring an 80mm inside diameter ring main with both 63 and 32mm drops to serve the various grinding and drilling workstations.

Where machines arrived from the old location complete with service air pipework, this was coupled to the Teseo supply lines to speed installation.

Crittall's 150 production staff completed their move in four months and maintained steel window production at 350 window frames per day thanks to the easy-to-install Teseo modular airline pipework system.

Not what you're looking for? Search the site.

Back to top Back to top

Contact Teseo UK

Related Stories

Contact Teseo UK

 

Newsletter sign up

Request your free weekly copy of the Engineeringtalk email newsletter ...

Visit the Energair Solutions web site

Search by company

A Pro-talk Publication

A Pro-talk publication